Relocation Case Study
Goal:
Develop and document a ROI and timeline associated with the migration and transition of all data center functions and servers to a new data center location
Situation:
Executive management had security and space utilization concerns about their current data center facilities and needed a thorough and comprehensive cost benefit analysis to facilitate their decision making process regarding a potential data center relocation.
Solution:
The David-Kenneth Group was engaged to provide an assessment and subsequent proposal for relocation of their existing data center to a new facility.
Engagement Model:
Outsourced
David-Kenneth Group Value Added:
- Experienced Data Center Migration Program Manager assigned to lead the assessment and analysis
- David-Kenneth’s DCM Team Cost Estimator and Executive Decision Making Matrix tools utilized
- Report and proposal produced identifying benefits, cost, timeline and potential risk
- Presentation made to Executive Management
- Technical resources remained on-site to address identified problem areas.
- Provided coaching and mentoring to team members
Bottom Line:
- Relocation of data center delayed for 1year
- Problem areas identified and addressed
- Focus made the difference
Reference available when appropriate